Excerpts from the
Hidden Lake
Drainage Study
Preliminary Engineering Assessment
Prepared by:
HRP Associates, Inc.
167 New Britain Avenue
Plainville, CT 06062
June 18, 2002
The Hidden Lake Drainage Study was
commissioned after the 2002 annual meeting as part of the continued program
to maintain the quality of the lake and in accordance with the Ecological
Survey conducted in 1995. The Association is now in the second round of
four-year septic tank pumping, and recently completed the weed removal project
in the West Cove. Road drainage improvements are the next phase in our
long-range plan to insure our lake is healthy for years to come.
Area 1
This area includes the eastern shoreline
of the lake, and properties on and accessed by East Shore Drive. We noted
several forms of drainage control in place, however they are not all
hydraulically connected. Most of these individual systems do not provide any
benefit to directing storm water directly to the lake or provide any form of
sediment protection or removal. Therefore, the pipes were often clogged by
obstructions such as silt and leaves, or collapsed. We observed various types of
piping installed at spot locations, including concrete pipe, corrugated plastic,
metal, and PVC. Recent roadway improvements hinder sheet flow, thereby trapping
storm water in some specific locations along East Shore Drive. Several drainage
swales along this section were eroded and the bottom and sides were unprotected.
Area 2
This area includes the southwestern
shoreline along Shore Drive and areas west of the masonry dam. Several drainage
structures were noted during the field visit. They appear to be operational and
functioning as a hydraulically connected system. In the vicinity where the pipes
discharge to the lake, we observed open drainage channels which were well
defined, but no protected from erosion.
Area 3
This area includes the northwest
shoreline along West Shore Drive from Hidden Lake Road to the beach. It was
noted that this area is generally much higher in elevation than the lake. This
change in elevation allows storm water to drain away from individual property
owners. Once again, we observed that the drainage swales into the lake were
unprotected and showed signs of erosion. The general sizes of the swales
indicate that and abundant volume of water discharges during a storm event.
Area 4
This area includes the northerly
shoreline and properties situated to the east of West Shore Drive. Portions of
this area also are generally higher in elevation than the lake. At the end of
West Shore Extension, at a substantially lower elevated area, there is evidence
of an inadequate drainage system. The prior storm event created or contributed
to an eroded path from a natural swale. Evidence of debris collected on the
roadway indicates that the cross culvert at the end of this roadway is probably
under capacity or clogged, and that storm water flows over the roadway to get to
the lower elevations. There appears to be a drainage system in place at the
intersection of West Shore Drive and West Shore Extension, however, silt and
leaves have clogged the system making it inoperable.
Recommendations
General
Many of the drainage problems observed
around the lake result from the lack of engineered collection systems, and
clogging of pipes and trenches from the migration of silt. In general, we
recommend that the lake association develop and implement a regular maintenance
program that includes the periodic cleaning of pip inlets and catch basins.
Historically, silt migration has been a significant concern at Hidden Lake, and
therefore erosion control will be an important factor for controlling runoff.
In our opinion, Areas 1 and 4 have the
most immediate need for improvements. Attached are example details of suggested
structural devices, which could be used to impede erosion and decrease the
amount of silt flowing into the lake. However, it is important that structures,
piping, and erosion control measures be designed as a system, and sized to
accommodate the calculated flows. Some surveying will also be required to define
site grades and pitch drainage systems appropriately. We recommend that any
future drainage systems which are constructed in the vicinity of the lake should
be designed by a licensed civil engineer.
Area 1
In Area 1, problems are occurring from
individual pipe systems that may be clogged or of inadequate size. Also,
discharge to the lake is occurring at several different drainage swales, which
promotes silt migration at multiple locations. HRP recommends that an engineered
system be designed to replace the existing system of non-connected pipes. The
new system could be situated along East Shore Drive, and route storm water to
one or more catch basins and discharge points. Discharge locations could be
lined with riprap to prevent scour. In order to decrease the discharge of
sediments, catch basins with three-foot sumps and/or a sedimentation chamber
could be designed. Also, installation of a subsurface drain with a protected
perforated pipe is suggested to eliminate the ponding along the roadway.
Area 2
At this location there is an existing
drainage system, and flooding only at certain isolated locations. HRP recommends
that this drainage system be cleaned to remove any sediments and leaves and to
improve all discharge locations by placing properly sized riprap to prevent
erosion. Although it is not an urgent area for improvement, future plans should
include replacing the drainage structures with three-foot sump catch basins
and/or the use of a sedimentation chamber prior to discharge into the lake.
Area 3
In Area 3, we did not observe any
specific flooding, but did note the condition of drainage swales. HRP recommends
that an engineering review of the drainage swales be performed in the future.
This would include a calculation of the runoff volume so that a properly
designed riprap scour hole or stilling basin could be constructed, to slow down
the velocity of the runoff and decrease erosion.
Area 4
Many of the problems we observed in this
area relate to the cleaning and management of the existing drainage system.
Several pipes were observed with partial or complete clogging by silt or
vegetation. Therefore, we recommend that a condition survey be performed and the
pipes first cleaned out. Release points of any culverts should be protected with
properly sized riprap to prevent scour. The cross culvert at the end of West
Shore Extension should be analyzed and sized correctly to prevent overtopping
and erosion of the shoreline. Drainage calculations should be performed and the
existing system augmented where necessary with additional piping.
SUMMARY
In summary,
most of the localized flooding and erosion problems around Hidden Lake are due
to inadequately sized or clogged pipe collection systems, and from the lack of
collection systems in certain areas. Some suggested improvements include:
-
A
regular program of cleaning the existing collection systems
-
Replacing
certain individual pipes with hydraulically connected systems, including
reducing the number of discharge points to the lake
-
Better
control of silt migration, including catch basins with sumps, sedimentation
chambers, using collection pipes with geotextile fabric protection, and
erosion control measures around outlet structures.
-
Engineering
design where necessary, to size system components for adequate capacity.
Estimated Costs for Drainage Improvements:
Area 1
Item # |
Item |
Pay Unit |
Quantity |
Unit Price |
Subtotal |
1 |
Catch Basin |
Each |
2 |
2,500.00 |
5,000.00 |
2 |
Sedimentation Chamber |
Each |
1 |
3,500.00 |
3,500.00 |
3 |
Drainage Pipe |
Linear Foot |
600 |
35.00 |
21,000.00 |
4 |
Subsurface Drains with Conduit |
Linear Foot |
500 |
30.00 |
15,000.00 |
5 |
Outlet Protection |
Cubic Yard |
7 |
55.00 |
385.00 |
6 |
Surveying/Engineering Services |
|
1 |
|
6,500.00 |
|
|
|
|
Project Total |
51,385.00 |
Area 2
Item # |
Item |
Pay Unit |
Quantity |
Unit Price |
Subtotal |
1 |
Catch Basin |
Each |
2 |
2,500.00 |
5,000.00 |
2 |
Sedimentation Chamber |
Each |
1 |
3,500.00 |
3,500.00 |
3 |
Drainage Pipe |
Linear Foot |
600 |
35.00 |
21,000.00 |
4 |
Outlet Protection |
Cubic Yard |
7 |
55.00 |
385.00 |
5 |
Clean Existing Drainage System |
Day |
1 |
900.00 |
900.00 |
6 |
Surveying/Engineering Services |
|
1 |
|
4,500.00 |
|
|
|
|
Project Total |
35,285.00 |
The complete Hidden Lake Drainage Study is
available in Adobe Acrobat PDF format. Click on the file below and it will open in Acrobat.
You may then print and/or save the file to your hard
drive or to a floppy disk. Click
Here To Get The Hidden Lake Drainage Study 565 Kb
You need Adobe Acrobat Reader to download the Bylaws
Don't have it? No problem, look below
Click
Here To Get Acrobat Reader Now
|