Comparison of Microsoft Project 98 with Project Scheduler 7 and SureTrak Project Manager 2.0
y=YES n=NO |
Microsoft Project 98 |
Project Scheduler |
SureTrak Project Manager 2.0 |
General Features | |||
Street price | $500 | $600 | $400 |
Online tutorial | y | y | y |
Year 2000-Compliant | y | y | y |
Project completion constraint | 12/31/49 | 12/31/63 | 13/31/69 |
Project Setup | |||
Wizards or project templates/Task outlining | y y | y y | y y |
Interactive manipulation of tasks and relationships | y | y | y |
Maximum number of tasks per project1 | Unlimited | 99,999 | 10,000 |
Can schedule recurring tasks/set priorities on tasks | y y | y y | y y |
Effort-driven/Duration-driven tasks | y y | y y | n y |
Supports Work Breakdown Structure (WBS) | y | y | y |
Duration measured in months/weeks | n y | y y | n y |
Duration measured in days/hours | y y | y y | y y |
Tracking and Modification | |||
User can se lead and lag times on constraints | n | y | n |
Baseline variances viewable on screen | y | y | y |
Tasks and resources can be filtered | y | y | y |
Resource Management | |||
Maximum number of resources per project1 | Unlimited | 99,999 | Unlimited |
Individual calendars for resources | y | y | y |
User can assign resources to a percentage of task | y | y | n |
User can define and assign material resources | n | y | y |
Can include overtime costs/materials costing | y n | y y | n n |
User-defined cost formulas | n | y | n |
Resource leveling (end date is pushed) | y | y | y |
Resource smoothing (end date remains the same) | y | n | y |
Leveling by date range | y | y | n |
Automatic task splitting during leveling | y | y | n |
Can show free float/total float/negative slack time | y y y | y y y | y y y |
Resource allocation histograms | y | y | y |
Multiple Projects | |||
Maximum number of project1 | 1,000 | Unlimited | Unlimited |
Automatic consolidation across multiple projects | y | y | y |
Projects can have persistent links to other projects | y | y | y |
Leveling across projects | y | y | y |
Can maintain resource pool for multiple projects | y | y | y |
Reporting | |||
Customizable standard reports | y | y | y |
Queries can be printed in reports | n | y | n |
Workgroup Capabilities | |||
Multiple user access to shared projects | y | y | y |
Update of schedule status via e-mail | y | n | y |
E-mail distribution of project information | y | y | y |
Publish/update project information via the Web | y y | y y | y y |
Customization and Integration | |||
Programming language/Macro recording | y y | n y | y n |
User-definable forms/menus/toolbars | y y y | y y y | n n y |
OLE client/server | y y | y y | y n |
ODBC support/Database server connectivity | y y | y y | y n |
Technical-support options | Free during regular support hours; after hours, $35 per incident; priority accounts available | Free | Free |
This comparison table is extracted from PC Magazine, 30 June 1998.
Task Usage Views
Task Usage View of Microsoft Project 98
Task List in Project Scheduler 7
Task List in SureTrak Manager 2.0