Project Start Date: Mon 11/9/98
Project Finish Date: Tue 12/1/98
ID | Task Name | Work | Duration | Start | Finish | % Work Complete |
---|---|---|---|---|---|---|
1 | Requirement Analysis and Specification | 88 hrs | 5 days | Mon 10/12/98 | Sat 10/17/98 | 100% |
2 | Proposed System | 24 hrs | 3 days | Mon 10/12/98 | Wed 10/14/98 | 100% |
1 | Mei Fun Wong | 24 hrs | Mon 10/12/98 | Wed 10/14/98 | 100% | |
3 | Non-funtional Requirements | 24 hrs | 3 days | Mon 10/12/98 | Wed 10/14/98 | 100% |
2 | Meng Yi Yee | 24 hrs | Mon 10/12/98 | Wed 10/14/98 | 100% | |
4 | Problem System | 8 hrs | 1 day | Mon 10/12/98 | Mon 10/12/98 | 100% |
3 | Marlainna Glenn | 8 hrs | Mon 10/12/98 | Mon 10/12/98 | 100% | |
5 | Current System | 16 hrs | 2 days | Tue 10/13/98 | Wed 10/14/98 | 100% |
3 | Marlainna Glenn | 16 hrs | Tue 10/13/98 | Wed 10/14/98 | 100% | |
6 | Compile project 1 | 16 hrs | 2 days | Thu 10/15/98 | Sat 10/17/98 | 100% |
1 | Mei Fun Wong | 16 hrs | Thu 10/15/98 | Sat 10/17/98 | 100% | |
7 | System Software and Design | 216 hrs | 9 days | Sun 11/1/98 | Thu 11/12/98 | 83% |
8 | Review Scope of System | 72 hrs | 9 days | Sun 11/1/98 | Thu 11/12/98 | 80% |
1 | Mei Fun Wong | 72 hrs | Sun 11/1/98 | Thu 11/12/98 | 80% | |
9 | Review Data Design | 72 hrs | 9 days | Sun 11/1/98 | Thu 11/12/98 | 80% |
3 | Marlainna Glenn | 72 hrs | Sun 11/1/98 | Thu 11/12/98 | 80% | |
10 | Review Architectural Design | 72 hrs | 9 days | Sun 11/1/98 | Thu 11/12/98 | 90% |
2 | Meng Yi Yee | 72 hrs | Sun 11/1/98 | Thu 11/12/98 | 90% | |
11 | Coding and Module testing | 120 hrs | 5 days | Fri 11/13/98 | Thu 11/19/98 | 0% |
12 | Accounts and Forms Coding | 40 hrs | 5 days | Fri 11/13/98 | Thu 11/19/98 | 0% |
3 | Marlainna Glenn | 40 hrs | Fri 11/13/98 | Thu 11/19/98 | 0% | |
13 | Children Database Forms Coding | 40 hrs | 5 days | Fri 11/13/98 | Thu 11/19/98 | 0% |
2 | Meng Yi Yee | 40 hrs | Fri 11/13/98 | Thu 11/19/98 | 0% | |
14 | Parents Database Forms Coding | 40 hrs | 5 days | Fri 11/13/98 | Thu 11/19/98 | 0% |
1 | Mei Fun Wong | 40 hrs | Fri 11/13/98 | Thu 11/19/98 | 0% | |
15 | Integration and System Testing | 56 hrs | 5 days | Fri 11/20/98 | Wed 11/25/98 | 0% |
16 | Integrating into an Application Software | 24 hrs | 3 days | Fri 11/20/98 | Mon 11/23/98 | 0% |
2 | Meng Yi Yee | 24 hrs | Fri 11/20/98 | Mon 11/23/98 | 0% | |
17 | Testing | 32 hrs | 2 days | Tue 11/24/98 | Wed 11/25/98 | 0% |
1 | Mei Fun Wong | 16 hrs | Tue 11/24/98 | Wed 11/25/98 | 0% | |
3 | Marlainna Glenn | 16 hrs | Tue 11/24/98 | Wed 11/25/98 | 0% | |
18 | Delivery and Maintenance | 24 hrs | 1 day | Thu 11/26/98 | Thu 11/26/98 | 0% |
19 | Demonstrate and Deliver new System to Daycare Center | 24 hrs | 1 day | Thu 11/26/98 | Thu 11/26/98 | 0% |
2 | Meng Yi Yee | 8 hrs | Thu 11/26/98 | Thu 11/26/98 | 0% | |
1 | Mei Fun Wong | 8 hrs | Thu 11/26/98 | Thu 11/26/98 | 0% | |
3 | Marlainna Glenn | 8 hrs | Thu 11/26/98 | Thu 11/26/98 | 0% | |
20 | Make appointment with Dr. Hines | 24 hrs | 1 day | Tue 12/1/98 | Tue 12/1/98 | 0% |
2 | Meng Yi Yee | 8 hrs | Tue 12/1/98 | Tue 12/1/98 | 0% | |
1 | Mei Fun Wong | 8 hrs | Tue 12/1/98 | Tue 12/1/98 | 0% | |
3 | Marlainna Glenn | 8 hrs | Tue 12/1/98 | Tue 12/1/98 | 0% |