Cahyadi
Qualification
-
Sepuluh Nopember Institute
of Technology (ITS), Surabaya Physics Engineering
-
Indonesian University
(UI), Jakart, (Master Computer Technical)
Training
-
1997 Trainee on Coal
Ash Behavior and Deposition Short Course University of North Dakota, Energy
& Environmental Research Center, Pittsburg, USA
-
1997 Instructor
on Training for Stack Sampling and Particle Sizing at UPT-LSDE, BPPT
-
1997 Instructor on in-house
Training for Stack Sampling and Ambient Monitoring at PT. SUCOFINDO (Persero)
-
1995 Instructor on Training
for Air Pollution Monitoring and Control in Industry at UPT-LSDE,
BPPT
Jobs
-
Instrumentation Engineer
at Distributed Control System (DCS) Rosemount System 3
-
Instrumentation and Control
Engineer at Pulverized Coal Combustion Testing Facilities
-
Instrumentation and Control
Engineer at Fluidized Bed Boiler
-
Instrumentation Engineer
at stack sampling for pollution monitoring
Work
Experiences
-
1998 Stack sampling for
Incinerator at PT. Indah Kiat (Serang)
-
1998 Stack sampling for
Hot Strip Mill Furnace at PT. Krakatau Steel (Persero) Cilegon
-
1996 - now Pulverized
Coal Combustion Testing at UPT-LSDE, BPPT
-
1996 - 1997 Slagging
and Fouling Investigation Project at PLTU Paiton, PLN-LSDE,BPPT.
-
1997 Stack sampling on
Fluidized Bed Combustor at UPT-LSDE , BPPT
-
1996 Flue Gas sampling
on Coal Fired Power Plant at PLTU Suralaya
-
1995 - 1996 Designing
Computer Based Instrumentation and Control at Fluidized Bed Boiler
-
1994 - 1997 Research
of Peat Combustion at Fluidized Bed Boiler