Road 45 - Cost Estimation by Sections

Ben Shemen - Modi'in

three lane tunnels (750 meters long) agricultural passages, Modi'in interchange

Start: 2000

End: 2003

Total cost: 238 million NIS

 

Modi'in - Givat Ze'ev

three lane tunnels, four bridges, Givat Ze'ev interchange

Start: 1999

End: 2003

Total cost:729 million NIS

 

Giv'at Ze'ev - Atarot

one bridge/ agricultural passage

Start: 1998

End: 2000

Total cost:116 million NIS

 

Atarot - Ramot

two bridges

Start: 1998

End: 2001

Total cost: 45 million NIS

 

Atarot road No 60

Start: 1999

End: 2002

Total cost: 15 million NIS

 

Road No 60 - Mishor Edomim

Start: 1999

End: 2002

Total cost: 150 million NIS

 

Mishor Edomim - Almog junction

Start: 1999

End: 2002

Total cost: 120 million NIS

 

 

 